CD3 prioritization is an approach for scheduling work through a scarce resource that maximizes Return on Investment. (CD3 = CDx3 from Cost of Delay Divided by Duration).
WSJF (Weighted Shortest Job First) is a similar method which has been made widely known by SAFe (Scaled Agile Framework).
The solution in Targetprocess creates the following fields for Projects:
- Cost of Delay (the cost to bear as a result of delay in investment)
- Estimated Duration (how much time a project can take)
- CD3 = Cost of Delay / Estimated Duration
Views in this solution
Add the solution
This solution can be added from the Solutions Gallery, which is always available from the “Create” button in the bottom left menu of Targetprocess. If you are an on-site customer, the Solutions Gallery mashup has to be installed before you can add a solution.
Still have a question?
We're here to help! Just contact our friendly support team
Find out more about our APIs, Plugins, Mashups and custom extensions. Join our community of passionate users and even discuss directly with our developers.